Building the railway

Phase 1 : The initial layout

Construction of the main board.

An undercoat of paint.

Track laying in progress.

More track laying.

The start of scenic works.

The basic outline of the wharf board.

First coat of paint on the main board.

First coat of paint on the quarry board.

The start of scenic work on the main station.

Phase 2 : The (originally unplanned) extension

Construction under way.

The baseboard is complete.

First coat of paint.

Tracklaying finished.

The start of scenic works.

Progress on the scenic work.

The station and wharf areas are added.

More basic scenic work.

More basic scenic work.

Back to the Home Page

Photographs © Peter Boulter 2019

counter for wordpress